Module 1 – Eligibility Period

The MSBA Board of Directors votes to invite the district into this module based on the Statement of Interest for a project. The vote initiates a 270 day period for the district to complete requirements including initial compliance certification, creating a School Building Committee, completing an education profile questionnaire, summary of existing maintenance practices, design enrollment, community authorization to proceed and execution of the feasibility study agreement.

MSBA Funding Application

The City of Lowell submitted a successful statement of interest to the Massachusetts School Building Authority (MSBA) for Lowell High School in April 2014.  The City was invited by the MSBA in November 2015 to conduct a Feasibility Study.